# Monte Carlo Project Scheduler (mcps)
Monte Carlo Project Scheduler (mcps) is a command-line tool that runs Monte
Carlo simulations on project schedules to estimate completion times and effort
required. It helps project managers and engineers gain a better understanding of
potential project risks and timelines by providing a probabilistic analysis of
schedule durations and total work effort.
## Features
- **Simulate Project Schedules**: Run multiple simulations to estimate the
probability distribution of project completion times and total work effort.
- **Customizable Inputs**: Accepts project schedules in YAML or JSON formats,
with options to override certain parameters like the number of workers or the
number of iterations.
- **Visual Output**: Generates an ASCII-based cumulative distribution function
(CDF) graph, providing an easy-to-understand visualization of the simulation
results.
## Installation
### Prerequisites
You'll need to have Rust installed on your system to build the project. You can
install Rust using `rustup`:
```bash
curl --proto '=https' --tlsv1.2 -sSf https://sh.rustup.rs | sh
```
### Option 1: Install from Crates.io (preferred)
```bash
cargo install mcps
```
### Option 2: Clone and build the repository locally
```bash
git clone https://github.com/swaits/mcps.git
cd mcps
cargo build --release
```
The binary will be available at `target/release/mcps`.
## Usage
Once you have built the tool, you can use it by providing a project schedule
file in YAML or JSON format.
### Basic Usage
```bash
mcps example.yaml -i 100000 -w 10
```
This command runs the Monte Carlo simulation on the [`example.yaml`](./example.yaml) schedule file
with 100,000 iterations and overrides the number of workers to 10.
### Command-Line Options
- `-i, --iterations <iterations>`: Specify the number of iterations to run. Must be at least 100. Default is 50,000.
- `-w, --workers <num_workers>`: Override the number of workers specified in the schedule file.
- `-v, --version`: Print version information.
- `-h, --help`: Print help information.
### Schedule File Format
The tool accepts schedule files in YAML or JSON format. Below is an example of the YAML format:
```yaml
num_workers: 5 # for the purpose of scheduling simulation
estimate_confidence: 0.80 # confidence actuals will fall inside estimate bounds
tasks:
- id: DesignPhase
min_time: 1.5 # 1.5 days
max_time: 3.5 # 3.5 days
dependencies: []
- id: ImplementationPhase
min_time: 2.25 # 2.25 days
max_time: 4.75 # 4.75 days
dependencies: [DesignPhase]
```
This repo includes examples in [JSON](./example.json) and
[YAML](./example.yaml).
### Example Output
The tool generates an ASCII-based cumulative distribution function (CDF) graph,
which visually represents the distribution of project durations and effort:
![example output of mcps](./assets/output.png)
## Project Details
### Contributing
Contributions are welcome! If you'd like to contribute, please fork the
repository and make changes as you'd like. Pull requests are warmly welcomed.
### Issues
If you encounter any issues with the tool, feel free to open an issue on the repository.
### Acknowledgments
This tool was developed by Stephen Waits. Contributions and suggestions are
always welcome!
### License
This project is licensed under the MIT License. See the [LICENSE](./LICENSE) file for details.